DEADMAN'S BASIN WATER USERS ASSOCIATION

Board of Directors
William E. Bergin, President
Greg Seder, Vice President
Bob Lehfeldt - Robert T. Goffena - Chris Colson

Project Manager
Teri Hice
125 Autumn Road
Roundup, Montana 59072
(406) 323-3533



The Deadman's Basin Water Users Association (DBWUA) consists of 110 irrigators on the Musselshell River encompassing nearly 200 meandering miles between Shawmut and Mosby Montana. DBWUA diverts Musselshell River water into an off-stream storage facility, Deadman's Basin Reservoir, via an 11.5 mile supply canal and delivers contract water via two outlet canals, the 2.85 mile long Barber canal and the 9.5 mile long Careless Canal. Deadman's Basin reservoir has a total capacity of 72,220 acre feet at full pool. There are currently 40,500 acre feet of water contracted for from the reservoir.



Inlet Drop at Deadman's Basin Reservoir




CURRENT WATER INFORMATION

(updated 10/7/09 @ 6:30 a.m.)

Reservoir Storage
27,000 AF
Inflows
0 CFS
Outflows
0 CFS
Water Orders
0 CFS


To order water, please email DBWUA Project Manager Teri Hice at kthice@midrivers.com


NEWS UPDATE
(updated 10/7/09 @ 6:30 a.m.)

The Notice to Proceed was issued to the contractor for the Dam Rehabilitation on October 1st. The contractor has 90 calendar days to reach substantial completion. I am hopeful that I can start diverting into the reservoir in November. As soon as the contractor has finished the work in the toe of the dam we should be able to begin filling the reservoir.

The outlet structure in the Barber Canal 80' drop held up through the end of the season. Although it is need of further repairs, it isn't as bad as I expected it to be after running 225 cfs over it for 90 days.

 

 

***************************************

Wiley Micks has resigned as District I Board Representative. Chris Colson will be the District I representative through the remainder of the fiscal year.

 

 

DAM REHABILITATION PROJECT

The Deadman's Basin Dam will be undergoing rehabilitation construction beginning October 1st. The outlet conduit will be extended 100 feet, drains will be installed, and ballast material will be added to the downstream face of the dam to increase the safety factor and reduce the uplift pressure.

The bids were let in May and Montana Civil Contractors of Belgrade has been issued a partial notice to proceed. The bid amount was $744,033.00. The project will be funded by a RRGL grant of $100,000.00, a DBWUA loan of $400,000.00, and the remainder by DNRC funds.

It is necessary to draw down the reservoir to a safe level for the construction, as the contractor will be excavating into the toe of the dam - the most critical location. The draw down level is elevation 3896 or 27,000 acre feet. It was derived at by evaluating piezometer and seepage data that has been collected over the past decade.

For comparison purposes, I began this season with 33,000 acre feet on January 1, 2009.

It was never anticipated that the reservoir would maintain this high level throughout the irrigation season due to cool weather and higher than usual decreed flows. Under normal conditions, more than 30,000 acre feet would have been released by now to satisfy irrigation demands.

The planning for the project has been in the works for the past two years. It is imperative to complete the repairs this fall in spite of a high level of storage in order to maintain safety, obtain the dam operating permit, and to take advantage of available funding.

 

THE DELIVERY PERCENTAGE FOR 2009 HAS BEEN INCREASED TO 90% AT YOUR HEADGATE

 

**********************

 

 

This will be the first year we will operate off of the new contracts. If your contract has not been approved by the Board of Directors, your diversion percentage will be calculated off of your original contracted amount.

 

**********

 

The water commissioner for contract and decreed water from Deadman's to Roundup (Zone 3) is John Rouane and the water commissioner for contract and decreed water from Roundup to Mosby (Zone 2) is Bob Goffena.

The MRDP Project began Monday, April 27th at 6:00 a.m.

 

Please be sure you call in your water order turn off just as you call in your water order

 

SNOW REPORTS

(updated 4/15/09 @ 10:00 a.m.) Excerpt taken from NRCS State Basin Outlook Report

March accumulated snow water was 172 percent of average. Snowpack conditions were near average and increased 14% from March 1st. Snow water content in the Musselshell Basin was 117% of average and 141% of last year.

AS OF APRIL 1, 2009...

Mountain and valley precipitation during March in the Musselshell was 139% of average and 457% of last year.

Bair reservoir storage was 62% of average and 165% of last year

Martinsdale reservoir storage was 81% of average and 1257% of last year

Deadman's Basin reservoir was 92% of average and 175% of last year

Assuming average precipitation, April thru July stream flows are forecast to average 86% to 108%

 

HISTORICAL DATA

Mid-March & Mid-April Data for 8 years:

Year
Storage For Mid-March
Inflow For Mid-March in CFS

Storage For Mid-April

Inflow For Mid-April in CFS

Diverted during the MRDP in AF
%Delivered
2009
44,401
55
47,099
80
  ** 90% **

2008

24,740
60
25,572
20
30,000

100%

2007
35,481
75
42,166
70
3,062
100%
2006
37,668
100
41,229
96
10,338
100%
2005
19,058
12
20,768
0
27,206
100%
2004
18,726
23
20,823
0
1,637
38%
2003
19,871
44
23,300
54
7,770
75%
2002
15,986
39
18,011
51
0
25%

 

 

** 90% ** of NEW WATER PURCHASE CONTRACTS

 



CONSTRUCTION / REHABILITATION

Construction at DB 21 wasteway by Martin Excavating
DB 21 wasteway completed in 2006



CURRENT PROJECTS

BARBER CANAL AT HEADGATE
(Click on thumbnail to see larger photo)

Below diversion headgate prior to construction
reshaping below diversion headgate
placing riprap below diversion headgate
rip rap placed and running 200 cfs

 

BARBER CANAL AT 80 FOOT DROP
(Click on thumbnail to see larger photo)

erosion at bottom of 80 foot drop
damage to concrete
displaced rip rap
6 foot deep erosion under concrete



2009 O & M PROJECTS

  • Realign first 435 feet of Careless Canal
  • Apply canal seal to largest seep areas in Barber and Careless Canals prior to water releases
  • Reshape canal bank and place fabric and rip-rap at Barber Canal headgate
  • Remove Russian Olive trees at confluence of Barber and Careless Canals
  • Clean sediment from lower Barber Canal
  • Weed management on all canals

 

 


© Copyright 2007 Deadman's Basin Water Users Association - All Rights Reserved